U.S. 13 Ramp Closures Set to Complicate Travel for Three Months

Traffic Alert

FALLS TWP, PA — Motorists traveling between Tyburn Road and U.S. 13 (Bristol Pike) in Bucks County should prepare for nearly three months of overnight ramp closures beginning Tuesday, December 1, as the Pennsylvania Department of Transportation (PennDOT) starts rehabilitation work on the bridge carrying U.S. 13 over Tyburn Road.

At a Glance

  • Roads Affected: Eastbound Tyburn Road to Northbound U.S. 13 (Bristol Pike) ramp and Westbound Tyburn Road to Southbound U.S. 13 (Bristol Pike) ramp.
  • Dates: Tuesday, December 1, 2026, through Friday, February 26, 2027, Sundays through Fridays.
  • Times: 8:00 PM–6:00 AM the following morning.
  • Reason: Bridge rehabilitation, structural repairs and drainage improvements.
READ:  I-95 Ramp Closures Threaten Overnight Delays in Delaware County

During the scheduled overnight work, the ramp connecting eastbound Tyburn Road to northbound U.S. 13 will be closed. Drivers will be directed to use Tyburn Road, Bristol Road and Pennsylvania Avenue to reach their destination.

The ramp from westbound Tyburn Road to southbound U.S. 13 will also be closed during the scheduled work periods. Motorists will be directed to use Tyburn Road, New Falls Road and Penn Valley Road.

PennDOT warns that backups and delays may occur near the construction areas and along both detour routes. Drivers should allow extra travel time and follow posted detour signs.

READ:  I-76 West Closure Threatens Thanksgiving Week Travel in Philadelphia

The rehabilitation will include repairs to the bridge’s fascia beams and drainage system, including the southwest inlet. Crews will also replace a section of slope pipe, backfill the slope, replace guiderail posts and perform pavement repairs.

The 72-year-old, three-span bridge measures 148 feet long and 77.5 feet wide. It carries more than 24,630 vehicles daily, and its superstructure is currently classified in poor condition.

The work is part of PennDOT’s $16.2 million program to rehabilitate 14 bridges across Bucks, Chester, Montgomery and Philadelphia counties.

READ:  I-95 Ramp Closures Threaten Overnight Delays in Delaware County

Loftus Construction Inc. of King of Prussia is the general contractor for the entirely state-funded project.

All scheduled construction activities are weather dependent.