Unionville-Chadds Ford Advances $164 Million School Project

Unionville-Chadds Ford School District

EAST MARLBOROUGH TWP, PA — The Unionville-Chadds Ford School Board voted unanimously Monday, November 16, to advance a proposed $164 million replacement for Charles F. Patton Middle School into its next design phase, moving one of Chester County’s major school construction projects forward, according to Chadds Ford Live.

The 7-0 vote authorizes continued design work on the proposed two-story school, which is scheduled for completion in May 2034. The project must also secure land-development approval from East Marlborough Township.

The district’s current budget estimate is approximately $164 million, although officials have identified potential savings of up to $5 million through bid alternatives and value engineering. The projected cost remains subject to revision as planning progresses.

READ:  Chester County Education Awards Draw 425 Nominations

James Whitesell, the district’s director of facilities, told school directors that the potential reductions are still being developed, Chadds Ford Live reported.

Construction is expected to proceed in phases over several years, beginning with new tennis courts and parking reconfiguration in 2029.

The district plans to construct new baseball and softball fields in 2030 before beginning construction of the replacement school building in 2032. Completion is targeted for May 2034.

The extended schedule places the district’s athletic facilities and campus infrastructure at the center of preparations before work begins on the school itself.

At an estimated $164 million, the project represents a substantial long-term capital commitment for the district. Its eventual financing could influence future borrowing requirements, operating budgets and property taxes.

READ:  Chester County Seeks Public Input on Climate Policy Update

The board’s decision advances the proposal beyond preliminary discussions and establishes the next stage of design development, although the project remains subject to township approval and further cost adjustments.

School directors also authorized several smaller infrastructure expenditures during Monday’s meeting.

The board approved nearly $28,000 to replace two rooftop compressors at the existing Patton Middle School, addressing equipment needs while planning continues for the replacement building.

Directors separately authorized $10,800 to evaluate and assess the wastewater-treatment plant and on-lot disposal system at Hillendale Elementary School.

READ:  Avondale Market Ordered to Stop Food Prep After Inspection

Another $38,050 was approved to replace kitchen equipment at three district elementary schools.

The additional expenditures total approximately $76,850, separate from the proposed middle school construction budget.

The decisions leave the district managing existing school infrastructure while advancing a multiyear replacement project that will require further design work, municipal review and financial planning.

For additional details on the board’s decisions and construction schedule, read Rich Schwartzman’s reporting for Chadds Ford Live at https://chaddsfordlive.com/2026/11/ucf-moves-forward-with-middle-school-design/.