EAST VINCENT TWP, PA — Pennsylvania American Water’s investment in a new Chester County water treatment plant has reached $143 million, approximately 16% above the figure announced in 2023, as the utility prepares to expand production capacity and address rising regional demand by mid-2027, WHYY reported.
The ratepayer-funded Lock 57 Water Treatment Plant is nearing completion three years after Pennsylvania American Water broke ground on what was initially described as a $123 million infrastructure project.
The investment addresses a supply constraint affecting northern Chester County and western Montgomery County. Daily water demand has reached 4.5 million gallons, exceeding the existing Shady Lane treatment plant’s capacity by 50% and leaving the utility dependent on neighboring systems to cover the difference.
Lock 57 will have a reported maximum production capacity of 11 million gallons per day and serve approximately 50,000 residents. Pennsylvania American Water’s original project announcement described a treatment capacity of 6.6 million gallons per day.
The service territory includes East Coventry, East Pikeland, East Vincent and West Vincent townships, Spring City and communities in western Montgomery County.
The project also positions Pennsylvania American Water to address federal drinking water regulations governing per- and polyfluoroalkyl substances, or PFAS. Dedicated treatment equipment will support the removal of those contaminants.
Operational changes include eliminating the use of pressurized chlorine gas in favor of sodium hypochlorite, introducing ultraviolet disinfection and implementing continuous water quality monitoring with automated contamination alerts.
The 52,000-square-foot facility represents the culmination of approximately a decade of development and will allow the utility to retire infrastructure dating to 1918, including equipment for which replacements are no longer commercially available.
“The infrastructure here has reached the end of its lifespan and doesn’t meet the demand that the region has,” John Keleman, Pennsylvania American Water’s manager of external affairs, told WHYY.
The Shady Lane plant will continue supplying customers until Lock 57 becomes operational. Pennsylvania American Water plans to demolish the existing facility following the transition.
For further coverage of the construction project and its treatment capabilities, read Zoë Read’s reporting for WHYY at https://whyy.org/articles/american-water-replacing-water-treatment-plant-near-royersford/.
Support the local news that supports Chester County. MyChesCo delivers reliable, fact-based reporting and essential community resources—free for everyone. If you value that, click here to become a patron today.